Substructure Successfully Completed in Nordhausen!

15. Dezember 2025

Despite demanding framework conditions, we successfully reached another important milestone in Nordhausen.

Due to difficult soil conditions and a high level of unexploded ordnance contamination, conventional pile driving for the substructure was not possible. Following extensive test drilling, the substructure was therefore constructed on concrete foundations.

This marks a major step toward the completion of the plant. We look forward to the next stages of construction.